How to Estimate Velocity?
Below are the steps to estimate velocity:
- Capture the total number of story points completed in the past 3 to 5 sprints.
- Consider only those story points that are 100% completed and marked as “Done” and not all the story points that are planned in the sprint.
- Take the average of the story points.
- This average story point is the velocity of the scrum team.
Example:
If the team completes the story points in the past 3 sprints are 28, 32, and 30.
Average story point = 28 + 32 +30
= 90 / 3
= 30
Thus, Velocity of scrum team is 30.
With the help of velocity, it becomes very easy to calculate how long will the team take to finish the final product release.
Velocity Chart Agile Scrum
The ability of agile project management to increase project flexibility and productivity is proven across industries and not just in software development. Velocity and velocity charts in agile play an important role when talking about software project management. There are numerous tools out there used by big organizations that can be used to ensure that their sprint is successful. The article focuses on discussing velocity chart agile scrum.
The following topics will be discussed here:
- What is Velocity in Scrum?
- Example of Scrum Velocity
- What is Velocity Chart in Agile?
- How to Estimate Velocity?
- Benefits of Agile Velocity Charts
- Limitations of Agile Velocity Charts
- Challenges of Measuring Agile Velocity
Let’s start discussing each of these topics in detail.